Language:


Employee Statistics

This report analyses the work carried out by each member of staff. It is a list of Project Transactions from the report period, sorted by Person, and showing the number of hours worked on Projects of each type (Invoiceable, Internal and Other).

Employee
Paste Special    Person register, System module
Range Reporting    Alpha
Enter a Person's initials to produce a report showing the work of a single employee.

Project
Paste Special    Project register, Job Costing module
Enter a Project Number to analyse who has worked on that Project.

Item
Paste Special    Item register
Enter an Item Number to restrict the report to a single Item, perhaps one that represents a particular type of work. The Item must be a Service Item or, if you select the Incl. Plain Items option (below), a Plain Item.

Item Group
Paste Special    Item Group register, Sales Ledger/Job Costing module
Range Reporting    Alpha
Enter an Item Group to restrict the report to Items belonging to that Group.

Customer
Paste Special    Customers in Customer register
Range Reporting    Alpha
Enter a Customer Number to analyse who has worked on Projects for that Customer.

Display Group
Range Reporting    Alpha
Enter a Display Group to produce a report showing the work of the employees belonging to that Display Group.

Period
Paste Special    Reporting Periods setting, System module
The report period.

Function
Use these options to control the level of detail shown in the report.
Detailed
This option lists all Project Transactions for each employee, sorted by employee, date and Item Number.

Overview
The report will contain one row per Person, with five columns. The first three columns show how many hours the Person spent working on Invoiceable, Internal and Other Projects respectively. The fourth column shows the total of the first three columns, and the fifth shows the percentage that is chargeable. This chargeable figure includes both invoiced work and work that is to be invoiced.

The figures in the first three columns are calculated by adding together the Registered Quantities of the Project Transactions entered in the Person's name. By default, only Project Transactions for time (i.e. Service Items) are used in the calculation. If the Incl. Plain Items option (below) is chosen, Project Transactions for Plain Items (i.e. purchases and materials) are included as well.

Per Item
The report shows for each employee the number of hours per Item.

Per Project
The report shows for each employee the number of hours per Project.

Per Item Group
The report shows for each employee the number of hours per Item Group. As in the Overview, separate figures are provided for hours spent on Invoiceable, Internal and Other Projects. The percentage of each Item Group total that is chargeable is also shown.
Specify
Use these options to include extra detail in the report.
Incl. Plain Items
By default, the report only lists Project Transactions that feature Service Items (i.e. time). Check this box if you want Project Transactions featuring Plain Items (i.e. purchases and materials) to be listed as well.

If you use this option, time (from Service Items) and quantity (from Plain Items) will be added together and shown as a single figure in the column headed 'Hours'. Select the Show Plain and Service Subtotals option below if you want separate total time and quantity figures.

Show Plain and Service subtotals
This option provides separate subtotals for Plain and Service Items per employee. You can use it together with the Incl. Plain Items option above.

You can only use this option in the Detailed version of the report.

Show Invoiced
This option includes a figure for total Invoiced Quantity in the report. You can only use this option in the Overview.

Incl. Prices
The default setting for this report is to provide analysis by quantity only (registered quantity, not invoiced quantity). Check this box to show the Sums from each Project Transaction as well.

This option has no effect when used with the Overview.
Registers
Use these options to specify whether Project Transactions created from Time Sheets or Activities or both are to be included in the report.